In the ORM process, at which step should risk decisions be made?

Prepare for the PMK-EE E6 Rank Petty Officer 1st Class Exam. Engage with multiple choice questions, detailed explanations, and study tips. Equip yourself with the knowledge you need to succeed!

The correct choice is Three because this is the step in the Operational Risk Management (ORM) process where risk decisions are made based on the analysis of potential risks identified in earlier steps. At this stage, individuals assess the risks, consider the potential outcomes, and weigh the benefits against the identified hazards.

By making risk decisions in this step, leaders can effectively prioritize actions that mitigate risks, ensuring that those with the greatest potential impact are addressed first. This approach allows for informed decision-making, promoting safety and efficiency within operations.

In contrast, earlier steps focus on identifying hazards and assessing risks, while later steps involve implementing controls and monitoring their effectiveness. Therefore, it is in step three where the culmination of risk assessment leads to actionable decisions regarding how to proceed within the parameters of acceptable risk.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy